TVA says new reactor construction on schedule

SPRING CITY, Tenn. (AP) - The Tennessee Valley Authority says work on a second reactor to the Watts Bar Nuclear Plant remains on schedule following a revision of completion estimates.

The federal agency recently released a fifth quarter update on Watts Bar 2 covering the work accomplished in the 15 months after the TVA board of directors approved continuing with construction of the unit in April 2012.

Officials say the plant is 80 percent complete. The estimated completion was projected between September 2015 and June 2016. It's now expected to be completed in December 2015.

The cost to construct the plant is also expected to stay within $4.5 billion after being increased from $2.5 billion.

TVA is the nation's largest public utility, supplying power to about 9 million people in Tennessee, Alabama, Mississippi, Kentucky, Georgia, North Carolina and Virginia.