Multi-billion Uranium Processing Facility needs redesign
Oct 3, 2012: Y-12 officials admit the new Uranium Processing Facility will have to go back to the drawing board after years of work due to design flaws related to the safety and size of the $6 billion plant.
http://www.wbir.com/video/1876245870001/1/Multi-billion-Uranium-Processing-Facility-needs-redesign
http://download.gannett.edgesuite.net/wbir/brightcove/29913744001/29913744001_1876301630001_upf.jpg?pubId=29913744001
Multi-billion Uranium Processing Facility needs redesign
Oct 3, 2012: Y-12 officials admit the new Uranium Processing Facility will have to go back to the drawing board after years of work due to design flaws related to the safety and size of the $6 billion plant.
Y-12mathenyoak ridgednfsbwbiruranium processing facilityRedesigndefense nuclear facilities safety boardy12UPFNews